Energy Monitoring in 48 Hours: Deploying It Without Stopping the Plant

How wireless energy metering can be installed over a single weekend without stopping production. An illustrative example of an IoT production and power monitoring system.

Energy Monitoring in 48 Hours: Deploying It Without Stopping the Plant

The Challenge: "You Can't Cut the Power" #

An illustrative example of an energy metering rollout with no power cuts; the figures are for reference only and do not come from a customer.

Scenario: a plastic injection molding plant.

Pain point: the electricity bill rising 15% a month with no increase in production.

Constraint: 24/7 operation. No downtime windows to run RS-485 cabling to the electrical panels.

If the plant also has to report under Chile's Energy Efficiency Law 21.305 (which requires large energy consumers to report their consumption), metering panel by panel is the first step.

The Solution: Wireless IoT and Split-Core Sensors #

To hit the 48-hour deadline (Saturday/Sunday, when the load drops slightly but never stops), a 100% wireless architecture is chosen.

Hardware Used

  • Meters: 12 three-phase meters with LoRaWAN communication.
  • Current transformers (CTs): split-core type. They open like a clamp, so they can be installed around the cable without disconnecting it.
  • Gateway: 1 industrial LoRaWAN gateway, connected over 4G (so phase 1 does not depend on the customer's IT network).
  • Software: the iGromi dashboard.

Weekend Timeline #

Saturday 08:00 AM - Arrival

Safety briefing. Panels identified (chillers, compressors, main injection molding machines).

Saturday 10:00 AM - Physical Installation

Technicians install the split-core CTs. Time per panel: 15 minutes. No power cuts.

Saturday 3:00 PM - Network Commissioning

The LoRaWAN gateway is powered up on the building roof (high point). RSSI coverage is verified for every sensor.

Sunday 09:00 AM - Software Configuration

Sensor IDs are mapped in the iGromi dashboard. Electricity tariff costs are configured (peak vs off-peak hours).

Sunday 2:00 PM - "The Moment of Truth"

The plant manager opens the dashboard on his phone. He sees the live consumption of Injection Molder #4. "I thought that machine was down today," he says. It wasn't: it was drawing 40 kW idling because of an operating error.

Results (First Month) #

Immediate visibility enabled some low-hanging fruit:

  1. Chillers switched off: it turned out the chillers were being left on over weekends "by mistake." Shutting them off was a direct saving every month.
  2. Phase balancing: a panel with severe phase imbalance was found overheating the neutral (a fire risk).

Project payback: the first month's findings had already paid for a good share of the metering.

Topics

  • energy monitoring
  • industrial energy monitoring
  • power monitoring
  • wireless energy metering
  • split-core ct
  • production monitoring system
  • energy management software
Sebastián Carrillo

About the author

Sebastián CarrilloLead Hardware Engineer

Translates code into tightened screws. Leads on-site installations and designs iGromi's industrial gateways, solving problems where dust and vibration come into play.

@igromi · Free app

Secure industrial AI, on your plant’s phones.

  1. 1Request early access, free
  2. 2Pick your trade: maintenance, production or safety
  3. 3The AI reads, proposes and cites; a person decides
Request early access

No credit card. Your data stays yours.